POSTD_130316_023
Existing comment: NPM Gallery Expansion
Project History -- Planning
* Early 2007 -- Opportunity identified
** Capital City Brewery space available in 2011
* Sept '07 - May '08 -- SmithGroup feasibility study
* June '08 - July '09 -- NPM fundraising to satisfy USPS that project could be executed
* Aug '09 -- Approval by SI Regents, completion of lease negotiations with USPS, finalization of lease negotiations with USPS, finalization of scope, budget ($18 m), schedule (Jan '13 opening)